EC&I Design, Calculations, Equipment specification, Commissioning & Project Management for a Chemical Site in West Yorkshire.

The site was installing 2 off new Reactors, associated services including scrubbing systems, pressure vessels and cooling towers to increase the current manufacturing capability on site. The project was a 2 year build phase and values approximately £5M.

Motor Control Centre’s, Trace Heating, SIL Rated Trip Systems, conventionally wired equipment, intrinsically safe remote IO, Hard wired trip systems, flame proof equipment all part of the scope of deliverable.

The designs were to confirm with BS EN 60079 relevant parts, IEC 61508 Safety related standard, BS7671 Latest edition of the wiring regulations and BS EN 62382 latest edition for the Electrical & instrument loop testing.